Customer: 

Global Blue-chip Company 

 

Site Type:

Office building 34000 meter sq. 

 

Coverage Requirement:  

Full Multi-operator / Multi technology DAS inbuilding solution.

​

Building Description:  

Mutli-level, 4 storey building with additional 2 car park levels  & basement. Open plan area with glass and wood partitions. Building deigned to high spec , visually cables had to astatically fit. Cater for a max of 3000+ staff & visitors 

​

Project management: Fully project managed by Surecom, designed by our professional radio engineers 

 

Solution Description:

Design, installation and commissioning and full handover of an in-building repeater solution to provide full coverage, capable of all mobile coverage up to 2100Mhz.Hybrid active passive solution. Approve by all mobile operators  

 

Responsibilities: 

  • Role PSDS 

    • Responsibilities: Solution Design (TEMs walk test, iBuildnet design coverage predictions, Antenna location verification – CW testing, BOM, MNO Design approval.)

  • Role PSCS 

    • Responsibilities: (BOM logistics-onsite), Main Contractor liaison and communication– site in construction phase, H&S compliance supporting site main contractor rules and co-operation to allow for working alongside other companies on site, Sample installation of the cable and antenna to support and agree methodology. 

    • Installation of solution to the design specifications (Cable Fibre & power), antennae, Radio units). Inclusive of “as build” handover.

    • Commissioning – Cable testing (Sitemaster & fibre), commissioning & optimisation, handover - walk and coverage 

    • Project management – Daily & weekly on-site meeting, weekly & monthly checkpoint & highlight reporting-6.

    • Responsible for RBS install for Vodafone and integration into DAS and optimisation

    • Integration of 3 Ireland RBS into DADS and optimisation

    • Instillation and integration of repeater solution for Meteor(now Eir)

    • Installation phase start date pushed back so reduced install time from 3 months to 1 month to meet deadline ( delays due to building contractors issues )

  • Team 

    • Project Manager  

    • Design Engineer X 2

    • Installation team of 16 men

    • Health and Safety Officer

    • Installation window 3 weeks 



       